How landscapers can protect their margins

11 hours ago
3 min read

With rising prices and surcharges applied to essential materials, it can be difficult for landscapers to protect margins and keep clients happy. This article by Ben Rickard of The Building Hub provides some timely advice


We're hearing from a lot of landscapers that supplier surcharges are making it hard to quote accurately, let alone hold a margin. Fuel-related surcharges are turning up on concrete, aggregates, pavers, soil and timber, sometimes after you've quoted and committed to the order.


Price rises and cancelled jobs are commercial risks, not insurable events, so your insurance is no help. The protection has to come from the terms and conditions in your quotes and contracts.


The Problem


Three things tend to go wrong:


1. Price creep between quote and purchase You quote in September, the client signs in October and by the time you order in November the supplier has increased or added a fuel surcharge. On a fixed price that increase comes straight off your margin.


2. The client won't accept the increase If you try to pass the surcharge on to the client, they may either refuse to pay it, ask to scale back the job or pull out altogether. By then you may have already ordered, committed resources and turned away other jobs.


3. Materials you can't send back Bulk deliveries such as aggregates, soil and bark generally can't be returned once they're tipped on site. Special-order items are often non-returnable, too. Even where returns are allowed, you may have to pay the transport costs to send them back.


What’s the solution?


The number one way to manage your risk is to have written (and signed) terms and conditions with your customers. These outline the risk and allow you to agree what happens in the case of price increases, including who bears the cost. A proper written contract is your best defence. Here’s how you can upgrade your contracts.


1. Put an expiry date on every quote 30 days is common. After that, the price is subject to re-quote.


2. Include a price adjustment clause It should let you pass on supplier price increases and surcharges that apply after the quote is accepted (with the supplier's invoice as evidence). Keep it fair. Give the client the right to cancel if the increase goes over a set amount, say 10%. But be careful! One-sided price clauses can fall foul of unfair contract terms rules in the Fair Trading Act.


3. Use provisional sums and/or a contingency  A provisional sum is an estimate that's adjusted to the actual cost. The client sees the risk upfront instead of you having to carry it. The same applies with a contingency.


4. Take a deposit that covers materials Don't order, especially anything non-returnable until the deposit is paid and any price change has been agreed.


5. Spell out cancellation and variation terms If the client cancels, your contract should stipulate that they must pay for any work completed, materials you’ve already ordered that can't be returned, plus any return freight costs for materials that can. Variations must be in writing with the price agreed before you order. 


Get a lawyer to look over your standard terms once. It's a small price to pay compared with one job going wrong.


If it happens anyway


Talk to the client early, show them the supplier's invoice and record any agreed price change in writing. If they cancel, invoice for the costs your contract allows. Then return what you can and use anything you can't on another job to reduce the loss.


Know your supplier's terms 

Check which surcharges they can apply, whether you can lock in a price for a large order and which materials can be returned.


In a nutshell

You can't control fuel prices but you can control who carries the risk. Quote expiry dates, a fair price adjustment clause, material deposits, provisional sums and contingencies with clear cancellation terms. These measures will protect your margin far better than just hoping prices will stay stable.